For the purpose of this Agreement, an “Event of Force Majeure” means any circumstance not within the reasonable control of the Party affected, but only if and to the extent that (i) such circumstance, despite the exercise of reasonable diligence and the observance of Good Utility Practice, cannot be, or be caused to be, prevented, avoided or removed by such Party, and (ii) such circumstance materially and adversely affects the ability of the Party to perform its obligations under this Agreement, and such Party has taken all reasonable precautions, due care and reasonable alternative measures in order to avoid the effect of such event on the Party’s ability to perform its obligations under this Agreement and to mitigate the consequences thereof.

Instances of Force Majeure

Events of Force Majeure shall include, but not be limited to:

(a) the following Natural Force Majeure Events:

  • fire, chemical or radioactive contamination or ionising radiation, earthquakes, lightning, cyclones, hurricanes, floods, droughts or such other extreme weather or environmental conditions, unanticipated geological or ground conditions, epidemic, famine, plague or other natural calamities and acts of God;
  • explosion, accident, breakage of a plant or equipment, structural collapse, or chemical contamination (other than resulting from an act of war, terrorism or sabotage), caused by a person not being the affected Party or one of its contractors or subcontractors or any of their respective employees or agents;
  • to the extent that they do not involve the UK or take place outside of the UK, acts of war (whether declared or undeclared), invasion, acts of terrorists, blockade, embargo, riot, public disorder, violent demonstrations, insurrection, rebellion, civil commotion and sabotage;
  • strikes, lockouts, work stoppage, labour disputes, and such other industrial action by workers related to or in response to the terms and conditions of employment of those workers or others with whom they are affiliated save, when such event is directly related to, or in direct response to any employment policy or practice (with respect to wages or otherwise) of the party whose workers resort to such action;
  • in relation to the Concessionaire, non-performance by a counter-party to a contract relating to the Concessionaire’s Business by reason of an event or circumstance that would constitute a Natural Force Majeure Event under this Agreement; and

(b) the following Political Force Majeure Events:

  • to the extent they take place in the UK, acts of terrorists, blockade, embargo, riot, public disorder, violent demonstrations, insurrection, rebellion, civil commotion and sabotage;
  • to the extent that they are politically motivated, strikes, lockouts, work stoppages, labour disputes, or such other industrial action by workers, save in relation to the Concessionaire, when such event is directly related to, or in direct response to any employment policy or practice (with respect to wages or otherwise) of the Concessionaire;
  • failure or inability of the Concessionaire to obtain or renew any Consent, on terms and conditions as favourable in all material respects as those contained in the original Consent relating to the Concessionaire’s Business (other than due to a breach by the Concessionaire of any of such terms and conditions);
  • any action or failure to act without justifiable cause by any Competent Authority, other than a court or tribunal(including any action or failure to act without justifiable cause by any duly authorised agent of any Competent Authority, other than a court or tribunal);
  • expropriation or compulsory acquisition of the whole or any material part of the Concessionaire’s System or Investor’s shares in the Concessionaire, except where such appropriation or compulsory acquisition is on account of contravention of law by the Concessionaire or by the Investor;
  • any legal prohibition on the Concessionaire’s ability to conduct the Concessionaire’s Business, including passing of a statute, decree, regulation or order by a Competent Authority prohibiting the Concessionaire from conducting the Concessionaire’s Business, other than as a result of the Concessionaire’s failure to comply with the law or any order, Consent, rule, regulation or other legislative or judicial instrument passed by a Competent Authority;
  • in relation to the Concessionaire, non-performance by a counter-party under a contract relating to the Concessionaire’s Business by reason of an event or circumstance that would constitute a Political Force Majeure Event under this Agreement,

provided that breakdown of plant or equipment (unless itself caused by an Event of Force Majeure), or unavailability of funds, shall not constitute an Event of Force Majeure.

Effects of an Event of Force Majeure

Either Party shall be excused from performance and shall not be in default in respect of any obligation hereunder to the extent that the failure to perform such obligation is due to a Natural Force Majeure Event.

Additionally, the Concessionaire, shall be excused from performance and shall not be in default in respect of any obligation under this Agreement to the extent that the failure to perform such obligation is due to a Political Force Majeure Event.

Notice of an Event of Force Majeure

If a Party wishes to claim protection in respect of an Event of Force Majeure they should, as soon as possible following the occurrence or date of commencement of such Event of Force Majeure, notify the other Party of the nature and expected duration of such Event of Force Majeure and shall thereafter keep the other Party informed until such time as it is able to perform its obligations. The Parties shall use their reasonable endeavors to:

(i) overcome the effects of the Event of Force Majeure;

(ii) mitigate the effect of any delay occasioned by any Event of Force Majeure, including by recourse to alternative mutually acceptable (which acceptance shall not be unreasonably withheld by either Party) sources of services, equipment and materials; and

(iii) ensure resumption of normal performance of this Agreement as soon as reasonably practicable and shall perform their obligations to the maximum extent practicable, provided that neither Party shall be obliged to settle any strike, lock out, work stoppage, labor dispute or such other industrial action by its employees.